By Abigail Goldring, Media Relations Staff
Eight years ago, the Hoboken PATH Station was devastated by the force of Superstorm Sandy. Today, well into the 2020 hurricane season and just ahead of NYC’s annual Climate Week, there are few lingering signs of the station damage from that perilous October night.
At the Hoboken Station, crews have been working through the pandemic to put the finishing touches on a formidable, multi-level flood protection system, a significant component of the agency-wide Sandy recovery program. The system is now set up to block several feet of water from flooding onto the tracks, which could disrupt service for hundreds of thousands of riders.
“Since 2009 we’ve addressed climate risks in project design, but Sandy brought a renewed urgency to our work,” said Port Authority Chief of Resilience and Sustainability Josh DeFlorio. “Through application of our Climate Resilience Guidelines, we’re continuing to harden our facilities to weather the impacts of climate change, including sea level rise and storm surge.”

During a storm, rushing water from the Hudson River can be blockaded from reaching the depths of the station in several ways. It might hit up against aquarium-thickness glass at the elevator or an aluminum stoplog system at the top of a staircase, or reach a flexible fabric barrier that’s been pulled over one of the staircases in anticipation of a storm. If the water ultimately makes it down the staircases, there are massive steel doors locked in place ahead of time designed to keep water from approaching the tracks. The heaviest steel door – at the staircase between NJ Transit and PATH – weighs 5,600 pounds.

The station’s upgrades are just a fraction of the enhancements taking place across the railroad to provide safer and more reliable service for riders.
In June 2020, the World Trade Center station reopened for weekend service six months ahead of schedule following extensive Sandy-related repairs. In June 2019, the new eastbound Harrison Station opened with specific flood mitigation measures already embedded into its design and retrofitted platforms to accommodate 9-car trains. The ability to accommodate longer trains at PATH stations is one of the key pieces of the agency’s $1 billion PATH Improvement Plan designed to reduce delays and improve the customer experience.
“The new flood protection systems we engineered are designed to help us get the railroad back up and running as quickly and safely as possible,” PATH Senior Project Manager Glenn Mack said. “It will now take us significantly less time to get the station ready for service again compared to what we faced after Sandy.”
The project is ahead of schedule, due in part to recent lower PATH ridership and the PATH team’s steady commitment throughout the pandemic to completing the project.

“We took advantage of the fact that fewer people were moving in and out of the station as we advanced our resilience work at the Hoboken PATH Station and all across the system,” said Damian McShane, PATH’s Assistant Director for Capital Projects Management. “I’m really proud of the hard work our teams put in to enhance the operational safety at Hoboken through this hurricane season and every hurricane season to come.”